GO HEAVY TRAILER: 400tons load capacity girder bridge with 24 axle lines modular trailer model V3 transported 390 tons tank
Project Introduction: The tank was 20 m long, 4.2 m wide and 4.75 m high. At Port Shanghai, J.Y. Group carried out all port services including stevedoring, lift plans and crane hire. J.Y. Group was also responsible for discharging the cargo from the hold of the vessel on to its 400 tons capacity girder bridge from GO HEAVY TRAILER. The 78-mile (125.5-km) move required the removal of street furniture, contraflow manoeuvres and temporary parking restrictions to allow the 60 m long, 5.6 m high loaded combination to pass safely. At the site, the cargo was delivered for installation via a pre-positioned trackway. J.Y. Group completed jacking and skidding operations to manoeuvre the tank onto the awaiting plinth. Equipment Mentioned: Modular Trailer Model V3: 24 axle lines Girder Bridge 400 tons capacity: 1 Unit Who Made The Girder Bridge and Modular Trailer in This Project? GO HEAVY TRAILER specialized in manufacturing heavy transportation equipment, like Modular Trailer, SPMT, High b...
评论
发表评论